FARGO PUBLIC SCHOOLS
Educating and Empowering All Students to Succeed
Task |
Date |
---|---|
Project Kick-off & Board Meeting |
8/29/2023 |
Steering Committee Meeting 1: Initial Data Review & Planning Process Introduction | 10/11/2023 |
Steering Committee Meeting 2: Data Review & Draft Framework for Options Development | 11/1/2023 |
Board Member 2x2 Interviews: Draft Framework for Options Development | 11/2/2023 |
Community Meetings: Data Review & Planning Framework | 11/14 - 11/16/2023 |
Survey #1 | 11/21 - 12/3/2023 |
Draft Initial Long-Range Facility Plan Options | |
Steering Committee Meeting 3: Review Draft Options/Survey Results & Prepare for Community Meeting and Survey #2 | 12/5/2023 |
Board Presentation: Long-Range Facilities Plan Options | 12/12/2023 |
Focus Groups (Identified populations most impacted by the Draft Options) | |
Community Meetings: Draft Options & Focus Group Feedback | 1/9 - 1/11/2024 |
Survey #2 | 1/10 - 1/24/2024 |
Steering Committee Meeting 4: Review Survey Data and Draft Recommendations | 2/6/2024 |
Draft Long-Range Facility Plan Recommendations | 2/8/2024 |
Board Member 2x2 Interviews: Review Draft LRFP Recommendations | 2/21/2024 |
Steering Committee 5: Review Draft Recommendations | 3/5/2024 |
Steering Committee 6: Finalize Draft Recommendations |
4/16/2024 |
Board Work Session | 5/23/2024 |
Present to Board (First Reading) | 5/28/2024 |
Present to Board (Plan Approval) | 6/11/2024 |